Hamilton Street Bridge Rehab - Rahway
POSTED:
Tuesday, November 22, 2022 - 3:00PM

Hamilton Street Bridge Scour Protection, Ra29
Union County Project #2018-008

Project description:

Staged installation of articulated concrete block matting in the existing waterway bound between existing bridge pier/abutments and new rip rap channel protection, as well as crack/spall repairs to existing bridge structure and roadway milling and paving.

Start date: December 1, 2022

Substantial Completion date 90 days: March 1, 2023

Traffic will permitted in the westbound direction. Traffic in the eastbound direction must use a detour route maitained by the contraxtor around the work zone. TRUCKS will have a serperately designated detour route.

View Detour Map

 

 

 



 

" U.C. Bear" and the slogans "We Work for You!","We're Connected to You!" and "Beat the Back-ups" are property of the County of Union
and cannot be used without the express permission of the Union County Board of County Commissioners.

To contact the Union County Board of County Commissioners, go to: ucnj.org